Aug 20, 2024
Commuter Lot 8 Green Parking Lot construction continued last week. The General Contractor (MYS) completed the removal of the existing aggregate base course. MYS removed the existing curb and gutter, exposed aggregate sidewalk, and salvaged the brick pavers. The two staircases that are to be reconfigured have been removed. Due to heavy rain last Thursday, the fine grading and placement of stone base were not completed.