Riverside continues Commuter Lot 8 green parking lot construction

Webp 133l1jayf1y7yoocidms1og5b3m7

Douglas Pollock President at Village of Riverside | Official website

Douglas Pollock President at Village of Riverside | Official website

Commuter Lot 8 Green Parking Lot construction continued last week. The General Contractor (MYS) completed the installation of the sidewalk and stairs.

This week, the contractor will complete paving the west entrance curb and sidewalk followed by brick installation. Brick installation will take six to eight days to complete.

The project is expected to be completed by mid-October.

Residents are reminded to use the west staircase to access the Metra platform. All other staircases are within the construction work zone and are closed until the project is completed.

The Village of Riverside acknowledges the disruption and inconvenience caused by this project. "If you have any questions or concerns, please feel free to call or email Village Engineer Tracy Wais at (847)878-0501 or Twais@cbbel.com," said a village representative. For updates, residents can check the Village website Notify Me • Riverside, IL • CivicEngage and sign up for E-Flash.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate