West Cook News

West Cook News

Friday, December 13, 2019

CITY OF COUNTRYSIDE: ComEd Conversion Project on Plainfield Road

Local Government

By Press release submission | Nov 24, 2019

Roadwork

City of Countryside issued the following announcement on Nov. 21.

ComEd is currently working on a conversion project where two 4kV Feeders are being retired and a new 12kV Feeder is being installed. The portion of work that runs through Countryside is on Plainfield Road, and is a part of the new 12kV Circuit. The staking along Plainfield Road is a designation of the Road Right of Way where construction crews are planning to install new conduit via directional bore which will be used to run cable for the new 12kV Feeder. Cook County permits were issued by HBK Engineering on October 22nd, and are pending final approval. Once the permits are received, the directional boring portion of the work will begin. The tentative date for construction to start is December 2nd. The duration of the project will last approximately six weeks, however, this may be extended due to unforeseen weather or field conditions.

Original source can be found here.

Want to get notified whenever we write about City of Countryside ?

Sign-up Next time we write about City of Countryside, we'll email you a link to the story. You may edit your settings or unsubscribe at any time.

Organizations in this Story

City of Countryside

More News