The Cook County Board of Commissioners approved funding today for transportation-related projects and initiatives led by the County’s Department of Transportation and Highways (DoTH). These vital projects boost economic development, build up regional transportation and improve the quality of life throughout Cook County.

The location, cost and scope of each project is listed below.

City of Northlake | $460,000

Construction of Hirsch Street bridge replacement over Addison Creek.

Village of Bedford Park |$100,000

Construction of 1.6 miles of sidewalk along 73rd Street between Massasoit Avenue and Sayre Avenue.

Village of Buffalo Grove |$40,000

Relocate pedestrian walkway that crosses Arlington Heights Road north of Dundee Road by approximately 400 feet and install new median refuge island serving Buffalo Grove High School and Cooper Middle School.

Village of Elk Grove Village |$125,000

Construction of a 1,000-foot bike path along Oakton Street, creating a continuous connection between the Busse Woods Forest Preserve and adjacent Pace bus stops.

Village of Justice |$69,720

Construction of Americans with Disabilities Act (ADA) compliant ramps and detectable warnings at 24 locations across the village.

Village of Lemont |$125,000

Preliminary engineering/planning services to separate the Centennial Trail from Canal Bank Road, providing a new, off-street path.

Village of Posen |$300,000

Reconstruct sidewalks and curbs to be ADA compliant between 144th and 149th Streets as well as Mozart Avenue to Kedzie Avenue.

Village of Phoenix |$200,000

Resurface and improve drainage along 155th Street, Second Avenue, Third Avenue and Walton Street.

Village of River Forest |$30,735

Install over 600 bike lane symbols and pavement markings in addition to 450 signs along bike routes.

Northfield Township | $200,000

Design/construction services to extend sidewalks on Sanders Road approximately 600-feet between Mission Hills and Oak Avenue.

Villages of Arlington Heights, Elk Grove Village, Palatine, Rolling Meadows, Roselle, Schaumburg and Streamwood | $16.3 million

Pavement resurfacing, curb and gutter replacement and ADA sidewalk improvements along:

  • Euclid Avenue at North Wolf Road
  • Central Road - New Wilke Road to Arlington Heights Road
  • Schaumburg Road - Meacham Road to Martingale Road
  • Schaumburg Road - Sutton Road to East Avenue
  • Euclid Avenue - Roselle Road to Plum Grove Road
  • Nerge Road - Roselle Road to Rohlwing Road
  • Roselle Road - Euclid Avenue to Palatine Road
Villages of Matteson and Richton Park | $1.4 million

Preliminary engineering for the reconstruction of a 1.5-mile corridor along Central Avenue from Sauk Trail to U.S. 30 (Lincoln Highway).

Bloom Township | $1.1 million

Preliminary engineering for the reconstruction of Sauk Trail from Western Avenue to Ashland Avenue, including the reconstruction of the bridge structure over the Thorn Creek.

To view DoTH’s 2022 interactive construction project map, visit: https://maps.cookcountyil.gov/hwyproject/

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS