Quantcast

West Cook News

Friday, November 22, 2024

River Forest Library Board OKs plans for carpeting, roof renovations

At a recent meeting, the River Forest Public Library Board green-lighted carpeting and entryway-roof renovation projects.

The River Forest Public Library Board of Trustees adopts policies to govern library programs and operations.

Below are the minutes from this meeting, as provided by the board.

Board of Trustees

River Forest Public Library

Facilities Committee Meeting Minutes

Wednesday, July 6, 2016 2:00 pm

Call to Order: Trustee Alice Calabrese Berry called the meeting to order at 2:00 pm.

Present: Trustees Alice Calabrese Berry, Joan O’Connor, and Claudette Zobel were present.

Also present were Director Sue Quinn and staff member Joanna Bertucci.

Minutes: Approval of June 1, 2016 Minutes. Trustee O’Connor moved to approve the minutes, Trustee Zobel seconded and the motion passed unanimously.

Old Business:

a. 2nd Floor Carpet Project

Director Quinn received three bids for the second floor carpeting project. The lowest bidder is Rieke Interiors at $33,425. The scope of the project will include re-carpeting the second floor and installing Johnsonite stair tread on the main lobby stairwell. The library will have to secure a dumpster.

Trustee O’Connor moved to approve the second floor carpeting and lobby stairwell project not to exceed $35,000. Trustee Zobel seconded and the motion passed unanimously.

The library will have to close Monday, December 26, Tuesday, December 27, and Wednesday, December 28 to complete the carpeting project. Trustee O’Connor moved to approve the library closure December 26, 27, and 28. Trustee Zobel approved and the motion passed unanimously.

b. Entryway Roof Replacement

Director Quinn received three bids for the entryway roof project. The chosen bidder is Trinity roofing to replace all three flat entry way roofs for $8110.

Director Quinn will investigate the terms of the 5 warranty.

Trustee O’Connor moved to approve the entryway roofing project not to exceed $8500. Trustee Zobel seconded and the motion passed unanimously.

New Business:

a. Sewerage ejector pump replacement

The sewerage ejector pump is the next project on the capital reserves project plan. The committee recommends that Director Quinn investigate and hire a plumber to look into the project the while Roosevelt Middle School campus project is underway.

The next meeting of the Facilities Committee will take place on Wednesday, August 10th at 2:00 pm.

Adjournment:

- The meeting was adjourned at 3:00 pm.

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS